CBCA 6822-FEMA; In the Matter of FLORIDA KEYS ELECTRIC COOPERATIVE Emergency Procurement; Reasonable Costs

Documentation Critical to Florida Utility's FEMA Reimbursement Arbitration - A Panel consisting of Judges Beardsley, Drummond, and Russell has determined the Florida Keys Electric Cooperative is entitled to partial reimbursement of its costs incurred to establish two full-service base camps to support recovery and power restoration efforts immediately following Hurricane Irma in 2017....
By: Baker Donelson