FERC Rejects PJM ELCC Proposal Based on Transition Mechanism; Establishes Paper Hearing Procedures
By EsqSocial Corporation 13/05/21
On April 30, 2021, FERC rejected PJM Interconnection, L.L.C.’s (“PJM”) proposed revisions to both its Tariff and its Reliability Assurance Agreement (“RAA”) to implement an Effective Load Carrying Capability (“ELCC”) construct for determining capacity values for Variable Resources, Limited Duration Resources, and Combination Resources. PJM also proposed to update its capacity value analysis annually based on variations in resource deployment and load. To account for changes in capacity values...
By: Troutman Pepper