Yes, Damages for Delay: Court Permits Delay Damage Claim to Proceed
By EsqSocial Corporation 04/04/25
A federal court in upstate New York is permitting a subcontractor’s delay claim to proceed notwithstanding a “no damages for delay” provision in the subcontract. The case, The Pike Company, Inc. v. Tri-Krete, Ltd., involves delay claims asserted by a subcontractor hired to install pre-cast concrete walls on a college dormitory project. The subcontractor alleges that the general contractor, The Pike Company, actively interfered with its work causing it to incur costs to overcome that interference...
By: Bradley Arant Boult Cummings LLP